The Joint Pilot Activities

Monitoring and Study on the Effects of Constructed Structure

  • Purpose: To maintain the structures effectively and to get good feedback for management and further activity
  • Outcome: It was confirmed that all the constructed structures functioned in a heavy rain as designed. The structure contributed to reduce the sediment.
  • Future: Monitoring and maintenance activates will be continued.
  • Topic: One heavy rain occurred in the Alenze area in the beginning of June 2018. It was confirmed that all the constructed structures functioned as designed. The wall-structures stopped the sediment flow and reduce their energy, the water channels limit the water and sediment flows to prevent any damages on the both sides of the channel, and the ford crossing structure protected the road completely and no damage was seen on the road.
Monitoring and Study on the Effects of Constructed Structure Anzali Wetland
Monitoring and Study on the Effects of Constructed Structure Anzali Wetland
Monitoring and Study on the Effects of Constructed Structure Anzali Wetland
Monitoring and Study on the Effects of Constructed Structure Anzali Wetland
Monitoring and Study on the Effects of Constructed Structure Anzali Wetland
Monitoring and Study on the Effects of Constructed Structure Anzali Wetland